• Location: South Iraq - 42” Crude Oil Pipeline West Qurna WQ1 to
Tuba Depot, 36” Crude Oil Pipeline Basra Refinery to PS-1
• Company: Basra Oil Company - BOC
• Contractor: Oil Projects Company - SCOP
• Duration: 2022
Scope of Work: Performed the Hot tapping process including ( Pre-fabrication,
Welding, Installation of Valves, Hydro Testing, & Hot Tapping ) for 5 points
28”x24” CL.150, 32”x24” CL.150, 36”x32” CL.150, 48”x32” CL.150, 36”x32” CL.150